Skip to main content

How to Assign and Track Vendor Work Orders/Tasks

Assign work orders to vendors from the Tasks page, track their progress from acceptance through to completion, communicate with vendors, review completion details, and view activity in the vendor's Audit tab.

Once your vendors are set up, you can assign tasks to them as work orders and track progress through to completion. This article explains how to assign a vendor, how vendors respond to work orders, and how to monitor their progress. For information on adding and configuring vendors, see How to set Up Vendors. To learn how vendors manage work orders through their own login, see How to use the Vendor Portal.

Please note: If a vendor does not appear in the list, check that they meet all four requirements above. For guidance on updating these settings, see How to set up Vendors.


Who Can Be Assigned

A vendor appears in the list for a task only when all of these are true:

  • The vendor's status is Active.

  • Assign Work Order is turned on for the vendor.

  • The vendor has a work category that matches the task's category. A task without a category can go to any vendor.

  • The task's building is one of the vendor's buildings. By default, a vendor is associated with all buildings.

Please Note:

  • A vendor that does not meet these rules is not listed, so a missing vendor usually means one of the four settings above needs a change on the vendor's page.

  • These settings are covered in 'How to set up Vendors'.


Assign a Vendor to a Work Order / Task

  1. In the SnapInspect Web App, click Tasks in the left menu to open the Task List.

  2. Find the task that needs a vendor. Use the available filters to locate the task you want to assign to a vendor, then click the task's title to open it.

  3. The task's detail page opens. On the right side, click the Vendor tab (next to Schedule, Comments, and Activity).

  4. A task with no vendor shows 'No vendor assigned' and the Assign Vendor button.

  5. Click Assign Vendor to open the vendor assignment window.

  6. Click Select a vendor… and choose a vendor from the Available list. The attachment field will become available once a vendor is selected.

  7. Set the Start Date and Due Date (optional).

  8. Enter any additional instructions for the vendor in the Notes field (optional).

  9. Under Attachments, drag and drop files into the upload area or click Browse to select files. These attachments will be available to the vendor when viewing the work order (optional).

  10. Click Assign Work Order.

Please note: If Assign Vendor is unavailable or a vendor is not listed, check that the vendor is Active, has Assign Work Order enabled, and meets the task's category and building requirements.

The vendor now shows on the Vendor tab with the dates, the status, and a Messages thread that starts with 'Work order assigned'. The vendor is emailed a link to the work order.

Please note: Start Date, Due Date, Notes, and Attachments are all optional. You can assign a vendor without them.


Waiting for Accept or Automatic Acceptance

Depending on your company’s Work Order Acceptance settings, work orders will either be accepted automatically upon assignment or start with a Waiting for Accept status, requiring the vendor to accept or decline them.

For information on configuring these settings, see the article on How to set up Vendors.


How the Vendor Responds

Vendors can manage their assigned work orders in two ways: directly through the emailed work order link or by logging in to the Vendor Portal. Regardless of the method used, all updates are reflected in the corresponding task in SnapInspect.

Option 1: Emailed Work Order Link (No Login Required)

This option allows vendors to view, accept, decline, and complete work orders directly through the link in their email, without needing to create an account or log in to the Vendor Portal. The following steps are completed by the vendor and require no action from your team.

  1. The vendor receives a Work Order Assigned email containing the property address, scheduled dates, and any instructions provided.

  2. The vendor clicks View Work Order.

  3. The work order opens directly in their web browser without requiring a login. The vendor can review the work order details and select Accept work order or Decline.

  4. Once the vendor accepts and confirms the work order, the Start work button becomes available. The vendor clicks this button and confirms to begin the work.

  5. Once work has started, the vendor must enter Completion notes and upload at least one photo or file under Completion photos and files.

  6. Click Mark completed to complete the work order.

Please note:

  • Both completion notes and at least one photo or file are required before the work order can be marked as completed.

  • The work order link is private to the assigned vendor. If the vendor is unassigned, the link will no longer be accessible.

Option 2: Through the Vendor Portal

Vendors with a Vendor Portal account can log in to view and manage all their assigned work orders in one place, rather than accessing each work order through an individual email link.

Please note: The following steps are completed by the vendor and require no action from your team.

  1. The vendor logs in to the Vendor Portal using their email address and password.

  2. From the left-hand menu, the vendor selects Work Order to view their assigned work orders, including the Source, Status, Start Date, and Due Date.

  3. Next to the relevant work order, the vendor clicks Action and selects View.

  4. The vendor reviews the work order details and selects Accept work order or Decline.

  5. Once accepted, the vendor clicks Start work.

  6. Once the work is finished, the vendor enters Completion notes and uploads at least one photo or file under Completion photos and files.

  7. The vendor clicks Mark completed.

Declining a Work Order

Regardless of whether the vendor is using the emailed work order link or the Vendor Portal, they can decline a work order while its status is Waiting for Accept. Selecting Decline opens the Decline work order window, where the vendor can provide an optional reason for declining. Once declined, the vendor is automatically unassigned from the task, allowing you to assign another vendor.


Messages and Files

You and the vendor share one message thread for each work order, starting from the moment you assign it.

  1. On the task's Vendor tab, open the vendor card by clicking its name.

  2. Under Messages, type your message in the box at the bottom and click Send. Use the paperclip to include a file.

The vendor writes from the Message box on the work order page or in the portal. Their messages appear in the same thread, together with the status updates.


Track the Work Order on the Task

The vendor card within the task's Vendor tab updates as the vendor progresses through the work order. You can track when the work order was accepted, started, and completed, including who completed the work.

Once the work order is complete, the vendor card will display Work completed. Click View to review the work order details, including the scheduled dates, original assignment notes, vendor completion notes, and any uploaded completion photos and files.


View Vendor Activity in the Audit Tab

The Audit tab provides a history of vendor activity, including what actions were taken, when they occurred, and who performed them.

  1. Navigate to Company Settings and select Vendors.

  2. Locate the relevant vendor, click Action, and select

  3. Open the Audit tab.

Each entry displays the date, event, description, and user associated with the activity. Recorded events include work order assignments, acceptances, declines, work started, work completed, and messages sent. The description also identifies the associated work order number and whether the vendor acted through the Vendor Portal or the emailed work order link. Use the Event, Done by, User, and Date filters to narrow down the audit history.


Unassign a Vendor from a Work Order

To remove an assigned vendor:

  1. Navigate to the Tasks page and open the relevant task.

  2. Select the Vendor tab.

  3. Click the Unassign icon in the top-right corner of the vendor card.

  4. Click Yes! to confirm.

Please note:

  • Unassigning a vendor immediately disables their emailed work order link and cancels any open bids associated with the task.

  • The Assign Vendor button will become available again, allowing you to assign another vendor.


If you have any additional questions or need support, please contact the team at support@snapinspect.com.

Did this answer your question?